Project — 38 Richmond Hills
Quick Facts
- Location: 38 Richmond Hills
- Service: Bathroom Renovation
- Duration: ~3 weeks
- Scope: Design, materials, installation, and final inspection.
Goals
- Reliable waterproofing for walls, floor, and niche areas.
- Walk-in shower or tub/shower combo with safe slip resistance.
- Adequate ventilation with quiet fan and exterior ducting.
- Moisture-resistant cabinetry and quartz tops.
- Neutral, bright palette for a clean modern look.
Materials & Specifications
- Waterproofing: cement board + liquid membrane; reinforced corners and niche.
- Tile: 12×24 porcelain on walls; 2×2 mosaic on shower floor for grip.
- Glass & Fixtures: 10 mm frameless glass; pressure-balanced valve set.
- Vanity: floating vanity with quartz top and undermount sink.
- Electrical: GFCI outlet and ESA-compliant circuits.
Process & Timeline
- Week 1 — Demo & rough-in: remove fixtures, prep substrate, plumbing and electrical.
- Week 2 — Tile & waterproof: apply membranes, tile install, grout and silicone.
- Week 3 — Fit & finish: set glass, vanity, lighting; testing and final clean.
Completed Project Photos
Tips & Care
- Use neutral-pH cleaners to preserve tile and quartz.
- Run the fan 20 minutes after showers to prevent humidity build-up.
- Inspect silicone annually and refresh when worn.